About the project
As part of our ongoing essential highway maintenance, Infrastructure and Environment (IE) will undertake work along Rue d’Aval and La Ruette de Faldouet in St Martin.
Patch repairs will be undertaken to strengthen the carriageway. The patch repairs will take place from 7.30am to 6pm on weekdays for 2 weeks, weather permitting.
The road will be closed from 3 April to 12 April 2024 between 9am and 2.30pm.
Lane closures will be in place from 2 April to 12 April 2024 outside of peak hours.
Following the patch repairs, a surface treatment will be applied to this section of carriageway. The road will be closed from 1 June to 2 June 2024 between 7.30am and 6pm. Works will take place during the weekends to minimise disruption to school buses.
Access chamber covers and gullies will then be reset between 4 June and 17 June 2024. Where chambers are in the middle of the carriageway, road closures will be required, otherwise works will take place under lane closures.
The working hours for road closures will be from 9am to 2.30pm.
Where lane closures can be undertaken safely, the working hours will be from 9am to 6pm. The surface treatment will be laid on the weekend of 1 to 2 June 2024 from 7.30am to 6pm.
After the surface treatment is laid the road will be closed to reinstate road markings on 18 June 2024 between 9am and 2.30pm.
Find more information on surface treatment on
road repairs and maintenance.
Map of Rue d'Aval and La Ruette de Faldouet surface treatment
Working hours and traffic management
More information will be provided as the project develops.
2 April | Advanced patching | Lane closures in place from 9am to 6pm, Monday to Friday |
---|
3 April to 12 April | Advanced patching | Road closures in place from 9am to 2.30pm following by lane closures from 2.30pm to 6pm |
---|
1 June to 2 June | Micro Asphalt Surface treatment | Road closures in place from 7.30am to 6pm over the weekend |
---|
4 June to 17 June
| Chambers and Gullys
| Road closures in place from 9am to 2.30pm during weekdays with road open as normal on weekends. Lane closures in place from 9am to 6pm where works can be completed safely during weekdays with road open as normal on weekends |
---|
|
18 June | Road marking | Road closure in place from 9am to 2.30pm
|
---|
Diversion routes
Westbound
Grande Route de Faldouet, La Grande Route de St Martin, Rue du Trot, Route de la Hougue Bie.
Eastbound
Route de la Hougue Bie, Rue du Trot, La Grande Route de St Martin, Grande Route de Faldouet.
Map of diversion route for Rue d'Aval works
Access
Access to all businesses and premises will be maintained where possible during the works.
Buses
Find more information relating to changes to the bus service on LibertyBus.