09 January 2026
July to December 2025
Prohibition Notices
1 Prohibition Notice was served relating to a failure by a Contractor to plan, manage and monitor the work at height of their employees and other workers in liaison with other contractors
Improvement Notices
5 Improvement Notices were served:
- 1 for the failure of a Contractor to provide supervision to employees to ensure work is done competently and safely
- 1 for the failure of a Contactor to suitably manage and monitor the construction phase of a project in liaison with sub-contractors
- 1 for the failure of a Principal Contractor to ensure that safe work method statements for high-risk construction work had been prepared in accordance with Regulation 19 of the Health and Safety (Management in Construction) (Jersey) Regulations 2016
- 1 for the failure of a Contractor to suitably plan, manage and monitor high-risk work of employees and subcontractors working to fulfil their contractual obligations
- 1 for a failure to safely store significant quantities of flammable liquids