Skip to main content Skip to accessibility
This website is not compatible with your web browser. You should install a newer browser. If you live in Jersey and need help upgrading call the States of Jersey web team on 440099.
Government of Jerseygov.je

Information and public services for the Island of Jersey

L'înformâtion et les sèrvices publyis pouor I'Île dé Jèrri

  • Choose the service you want to log in to:

  • gov.je

    Update your notification preferences

  • one.gov.je

    Access government services

  • CAESAR

    Clear goods through customs or claim relief

  • Talentlink

    View or update your States of Jersey job application

Cost of reviewing potential sites for the new hospital (FOI)

Cost of reviewing potential sites for the new hospital (FOI)

Produced by the Freedom of Information office
Authored by States of Jersey and published on 17 November 2015.

​Request

I would like to know how much has been spent on reviewing potential sites for the new hospital in the past five years please? I would like this to include assessing the sites and any plans that have been created when assessing them. Thank you.

Response

All Scheduled Public Authorities (SPA) are separate legal entities for the purposes of the Freedom of Information (Jersey) Law 2011. Therefore, if a request comes in via the States of Jersey central FOI unit it will be disseminated to the most relevant SPAs that are central States of Jersey entities. 

In respect of this request, Jersey Property Holdings who are at present under the Treasury and Resources Department have responsibility for the delivery of the Future Hospital capital asset project and are therefore the most appropriate department to handle and respond to your request.

The amount that has been spent reviewing potential sites for the new hospital in the past five years is as follows:

​2011£​0
​2012​£220,708
​2013​£413,485.05
​2014​£396,160.77
​2015 (Up to 30/9/2015)​£1,179,220.87
​Total​£2,209,547.69

The amount spent includes direct costs to external suppliers, an apportionment of project team costs, and overheads associated with the project team office and administration. Project team and project office costs have been apportioned on a percentage basis.