Skip to main content Skip to accessibility
This website is not compatible with your web browser. You should install a newer browser. If you live in Jersey and need help upgrading call the States of Jersey web team on 440099.
Government of Jerseygov.je

Information and public services for the Island of Jersey

L'înformâtion et les sèrvices publyis pouor I'Île dé Jèrri

Our Hospital Project Review issues report and recommendations

01 November 2022

​The review of the Our Hospital Project has issued its report and recommendations to the States Assembly. 

The review led by the Minister for Infrastructure, Deputy Tom Binet, found the current plan for a new hospital at Overdale is no longer affordable or appropriate within the funding approved by the States Assembly.

It recommended the plan be replaced with a phased development across two or more sites, including Overdale, Kensington Place and the existing hospital site at Gloucester Street. 

The review was ordered under the Chief Minister’s 100-day Plan to consider whether any changes can be made to the hospital project to deliver a more affordable and appropriate alternative.

The review took into consideration evidence from more than 60 key stakeholders and undertook visits to various healthcare facilities in Northern Ireland.

It found the Our Hospital Project is no longer achievable within the £804.5 million funding approved by the last States Assembly, and that it would cost between £70 million and £115 million more under current market conditions.

It found a simple relocation of the current plans to the existing hospital site at Gloucester Street would also be unaffordable and would face significant other challenges, including planning, and risk arising from working within and adjacent to an operational hospital site.

Ministers provided clear direction that construction of new hospital facilities should commence within the current electoral term, and the review did not consider a new site, as this would not have enabled the delivery of a new hospital within the required timescale.

It considered the following options

  • A single development of a new hospital at Overdale significantly smaller than the current plans 
  • A phased development of a significantly smaller hospital at Overdale
  • A phased redevelopment of the hospital at its current site
  • A phased redevelopment of the hospital at its current Gloucester Street site and on the adjacent Kensington Place site
  • A phased development over two or more sites including Overdale, Kensington Place and Gloucester Street 

The review found a phased development over two or more sites including Overdale, Kensington Place and Gloucester Street, if required, offered the best opportunity to make the scheme more affordable and appropriate, and to manage the risk of costs rising significantly once the project is underway. 

The report noted that it is challenging in the current uncertain financial climate to give precise figures in relation to the extent of saving that can be achieved.

But it identified the following potential savings at today’s prices from a phased development over two or more sites:

  • Up to £50 million from the reduced need for new road infrastructure and land acquisitions 
  • Up to £30-60 million from separating the scheme into smaller constituent parts, opening up procurement, including to more local contractors and enabling more competitive bids
  • Up to £15-30 million from future digital healthcare services delivery
  • Up to £15-30 million from modern methods of construction for some buildings
  • Up to £15-20 million from the market value of healthcare sites no longer required 

The report noted that a phased development would open procurement to smaller contractors, which would lead to more competitive bids and make it more possible for local contractors to participate, keeping more of the money spent within the Jersey economy. 

The review recommended the following schedule:

  • Phase 1 – Development at Overdale to be commenced within 24 months with a 36- month programme to completion
  • Phase 2A – Development at Kensington Place or Overdale to be commenced within 36 months with a 36-month programme to completion
  • Phase 2B - Development at the current hospital site at Gloucester Street to be commenced within 72 months, with a 24-month programme to completion. 

The review found that mental health services could be established at a separate standalone location and recommended a review of the requirements to commence immediately, with proposals on site within 36 months and a 24-month construction programme to completion. 

The review recognised that the existing Jersey General Hospital must be kept safe whilst the various developments are constructed and noted that additional funding is currently being made available for this in the event that it is required.

The Minister for Infrastructure, Deputy Tom Binet, said: “We believe we have identified a solution which will give Jersey the new hospital facilities it needs without significant delay, while keeping the costs affordable and risks managed in challenging economic times. 

“I would like to thank everyone who helped with this review and enabled us to complete it in such a short time.” 

Following the review a number of practical steps will now be taken, including the necessary design and decision making to put these proposals into effect. 

The review team was led by the Minister for Infrastructure, Deputy Tom Binet, and also comprised the Minister for Health and Social Services, Deputy Karen Wilson, and the Assistant Minister for Health and Social Services, Deputy Rose Binet.

Back to top
rating button