Skip to main content Skip to accessibility
This website is not compatible with your web browser. You should install a newer browser. If you live in Jersey and need help upgrading call the States of Jersey web team on 440099.
Government of Jerseygov.je

Information and public services for the Island of Jersey

L'înformâtion et les sèrvices publyis pouor I'Île dé Jèrri

  • Choose the service you want to log in to:

  • gov.je

    Update your notification preferences

  • one.gov.je

    Access government services

  • CAESAR

    Clear goods through customs or claim relief

  • Talentlink

    View or update your States of Jersey job application

Esplanade carriageway reconstruction work

About the project

As part of the ongoing highway maintenance by Infrastructure and Environment, the Esplanade’s carriageway is being reconstructed between the junction with Gloucester Street and the junction with Peirson Road.

The project is split into 4 sections and each section will be constructed during the school holidays. To minimise the disruption to traffic 2 lanes in each direction will remain open during the project.

We will implement a contra-flow system and provide diversions within the local area. The contra-flow system will be implemented and will remain in place 24 hours a day for the duration of the project.

Schedule of work for all sections

​Section
​Date
Detail​
Section 1 (completed)
Completed ​October half term 2021
Lane 1 and half of lane 2 westbound carriageway
Section 2 (completed)
​Completed October half term 2023
Lane 3, half of lane 2 and right turn lanes westbound carriageway
Section 3
​Provisionally October half term 2024
Lane 3 and half of lane 2 eastbound carriageway
Section 4 (completed)
​Completed October half term 2022
Lane 1 and half of lane 2 eastbound carriageway