About the project
As part of the ongoing highway maintenance by Infrastructure and Environment (IE), La Route de Ste Marie, La Verte Rue and La Rue des Buttes will be resurfaced in St Mary.
The works will start on Monday 12 August 2024 and should take 6 weeks to complete. The project will be delivered in sections to minimise disruption.
Working hours and traffic management
The working hours will be Monday to Friday, 7.30am to 10pm.
Section 1 La Verte Rue, between the junction with Eden Lane and Rue de la Rosière
| 12 to 20 August 2024
| Road closures in place all day
|
---|
Section 2
La Verte Rue, between the junction Rue de la Rosière and St Mary’s Primary School
| 20 to 23 August 2024
| Road closures in place all day
|
---|
Section 4
Unnamed road between La Verte Rue and La Route de Ste Marie
| 16 to 20 September
| Road closures in place all day
|
---|
Section 5
La Rue des Buttes, between the junction with Rue de la Frontière and the Co-op
| 23 to 30 August 2024
| Road closures in place all day
|
---|
Section 8
La Route de Ste Marie, between St Mary's Rectory and Rte du Carrefour a Cendre
| 2 to 12 September 2024
| Road closures in place all day
|
---|
Diversion route
A route through St Mary will be available at all times during the works.
Diversion route for section 1
Diversion route for section 2
Diversion route for section 4
Diversion route for section 5
Diversion route for section 8
Access
Access to all businesses and premises will be maintained where possible during the works.
Buses
Find information on changes to the bus service on
Liberty Bus.