Skip to main content Skip to accessibility
This website is not compatible with your web browser. You should install a newer browser. If you live in Jersey and need help upgrading call the States of Jersey web team on 440099.
Government of Jerseygov.je

Information and public services for the Island of Jersey

L'înformâtion et les sèrvices publyis pouor I'Île dé Jèrri

  • Choose the service you want to log in to:

  • gov.je

    Update your notification preferences

  • one.gov.je

    Access government services

  • CAESAR

    Clear goods through customs or claim relief

  • Talentlink

    View or update your States of Jersey job application

Breakdown of the Nightingale hospital costs (FOI)

Breakdown of the Nightingale hospital costs (FOI)

Produced by the Freedom of Information office
Authored by Government of Jersey and published on 25 June 2020.
Prepared internally, no external costs.

Request

A

Can you please confirm what the final cost of Nightingale Hospital wing in Jersey has been to the taxpayer?

B

Can you clarify how much was spent on off island consultants and give a breakdown of the reported £14M budget and if we actually remained within this budget?

C

Is the structure to remain Jersey property or will it be returned when no longer required?

Response

A

Invoices are still being finalised in accordance with the contract and it is therefore not possible to provide the final costs at this stage.

B

Only one off-island contractor has been appointed to date. We have not yet received their invoice. As stated in question A, invoices are still being finalised and it is therefore not possible to provide a final cost as this stage. However, the table below provides a breakdown of the original estimated £14.4 million and the actual monies paid to date, to the end of May 2020.

Construction Costs

​Estimated costs 2020

​Actual spend to End May

​Building hire and erection ​£1.0m£​0.5m
​Fit out costs ​£6.3m​£5.7m
​Medical equipment £4.8m £​1.2m
​Utility connections and upgrade costs £1.0m ​-
​Contingency£1.3m​​-

​Total 

​£14.4m

£​7.4m

 

It is anticipated that the project will remain within the £14.4m budget.

C

The structure is hired and will be returned once it is no longer required. However, there is an option to purchase the structure should the Government or Department wish to exercise it.