Skip to main content Skip to accessibility
This website is not compatible with your web browser. You should install a newer browser. If you live in Jersey and need help upgrading call the States of Jersey web team on 440099.
Government of Jerseygov.je

Information and public services for the Island of Jersey

L'înformâtion et les sèrvices publyis pouor I'Île dé Jèrri

  • Choose the service you want to log in to:

  • gov.je

    Update your notification preferences

  • one.gov.je

    Access government services

  • CAESAR

    Clear goods through customs or claim relief

  • Talentlink

    View or update your States of Jersey job application

Water treatment facility tender process (FOI)

Water treatment facility tender process (FOI)

Produced by the Freedom of Information office
Authored by Government of Jersey and published on 02 November 2021.
Prepared internally, no external costs.

Request

NMCN was selected to lead the upgrade of the wastewater processing facility at Bellozanne in November 2018, following concerns that it was failing to meet modern standards and may struggle as the population grows. Can you please tell me how many contractors tendered for this work and who made the final decision on who the contract was awarded to?

Response

Three contractors tendered for the project. The evaluation was carried out by the Tender Evaluation Panel consisting of 10 panel members. The decision was approved by the Chief Officer and the Director of Strategic Procurement.