Skip to main content Skip to accessibility
This website is not compatible with your web browser. You should install a newer browser. If you live in Jersey and need help upgrading call the States of Jersey web team on 440099.
Government of Jerseygov.je

Information and public services for the Island of Jersey

L'înformâtion et les sèrvices publyis pouor I'Île dé Jèrri

  • Choose the service you want to log in to:

  • gov.je

    Update your notification preferences

  • one.gov.je

    Access government services

  • CAESAR

    Clear goods through customs or claim relief

  • Talentlink

    View or update your States of Jersey job application

Les Quennevais School building contract (FOI)

Les Quennevais School building contract (FOI)

Produced by the Freedom of Information office
Authored by Government of Jersey and published on 27 July 2022.
Prepared internally, no external costs.

Request 

A

What form of building contract was used between client and contractor on the new Les Quennevais School?

B

Who designed the air conditioning i.e. was it a professional consultant?

C

Was a retention sum held back for the duration of the works and the rectification period in accordance with standard contract procedure?

D

Has the final account been completed and agreed and has retention been released? 

Response 

A

A Joint Contracts Tribunal (JCT) 2011 contract as amended and approved.

B

The building was not designed as fully air conditioned but a mix of natural and mechanical ventilation. The Information and Communications Technology (ICT) suites, hall, lecture theatre, Special Educational Needs (SEN), and conference suite only are fully air conditioned. This was designed by TNG Consulting Engineers as Performance Specified Works and priced and designed by them in conjunction with sub-contractor Brady and Gallagher and Breathable Buildings Limited.

C and D

Practical completion was issued 28th July 2020. The Certificate of Making Good Defects was issued on 4th May 2022, delayed beyond the usual 12-month period by the need to undertake works around school operational times and seasonal planting. A retention sum was held back until the Final Certificate was issued on 31st May 2022.


Back to top
rating button