Phase 8 of HMP La MoyePhase 8 of HMP La Moye
Produced by the Freedom of Information officeAuthored by Justice and Home Affairs and published on
29 April 2026.Prepared internally, no external costs.
Request 819875715
Please confirm whether the proposed “Outworkers” or pre-release facility (Phase 8) at HMP La Moye:
- Was completed as originally planned,
- Was cancelled, or
- Was replaced or modified.
Response
The originally proposed new purpose-built pre-release facility, which was proposed in 2019, has been cancelled.