TREASURY AND RESOURCES MINISTER
day surgery unit - budget transfers
1. Purpose of Report
1.1. The Minister is asked to approve budget transfers required to complete the proposed works to the new Day Surgery Unit at the General Hospital.
2. Background
2.1. The former Finance and Economics Committee, at its meeting of 11 August 2005, agreed a funding strategy for an enhanced scheme to extend the Day Surgery Unit.
2.2. The Committee agreed in principle to provide £500,000 from the capital reserve, of which £286,000 was earmarked and £214,000 retained as a provision against potential claims in respect of the Overdale project.
2.3. Two variations to the Day Surgery Unit have also been approved by the Minister for Health and Social Services, subject to funding approval. They are:
· An increase in the cost of cladding and expenditure due to stoppages affecting operations in the existing Day Surgery Unit has reduced the project contingency to an unacceptably low level. It is proposed that an underspend of £88,226 relating to the Cremator Replacement Project be transferred to the Day Surgery Unit project; and
· To bring the original project within budget the proposed upgrade of the existing Day Surgery Theatre was omitted. The Minister for Health and Social Services has identified £250,000 within that department’s 2007 Minor Capital allocation to undertake the works. The work will be undertaken as a variation to the existing contract, which is a more cost and time effect approach than undertaking a separate contract. The Minister is asked to approve the necessary budget transfer.
3. Comments
3.1. The final account for the Overdale project has been completed within the anticipated budget and the full £500,000 is available to be transferred from the Capital Reserve, as previously agreed in principle by the former Finance and Economics Committee.
3.2. The potential Cremator project underspend was identified in August 2005 when the Day Surgery Unit tenders were considered, but the final invoices for that project were not received until July 2006. No request for this balance to be transferred to the Day Surgery Unit project was tabled to the Minister until it was ascertained that it would not be required to support potential claims on the Overdale project.
3.3. The Day Surgery Unit has been a complex and high risk project that has been generally well managed. It has some five months to run until practical completion and has passed through the major risk period, but there is still the potential for unforeseen events to occur and claims to be tabled from the contractor. It is, therefore, considered prudent to increase the contingency sum available.
4. Recommendation
4.1. That the Minister approves the following budget transfers to the Day Surgery Unit project:
· £500,000 from the Capital Reserve - as agreed in principle by the former Finance and Economics Committee;
· £88,226 from the completed Cremator Replacement project; and
· £250,000 from the Health and Social Services Department’s 2007 Minor Capital allocation, to upgrade the existing Day Surgery Theatre.
5. Reason for Decision
5.1. The budget transfers are necessary to provide sufficient funding to complete the Day Surgery extension scheme and upgrade the existing theatre within the existing contract.
States Treasury Corporate Finance
14 February, 2007 for Decision Meeting 12/02/2007