Jersey Gas Company Ltd, La Route du Veule, St. Helier (EIA/2012/0721): Environmental Impact Assessment: Not Required

A formal published “Ministerial Decision” is required as a record of the decision of a Minister (or an Assistant Minister where they have delegated authority) as they exercise their responsibilities and powers.

Ministers are elected by the States Assembly and have legal responsibilities and powers as “corporation sole” under the States of Jersey Law 2005 by virtue of their office and in their areas of responsibility, including entering into agreements, and under any legislation conferring on them powers.

An accurate record of “Ministerial Decisions” is vital to effective governance, including:

  • demonstrating that good governance, and clear lines of accountability and authority, are in place around decisions-making – including the reasons and basis on which a decision is made, and the action required to implement a decision

  • providing a record of decisions and actions that will be available for examination by States Members, and Panels and Committees of the States Assembly; the public, organisations, and the media; and as a historical record and point of reference for the conduct of public affairs

Ministers are individually accountable to the States Assembly, including for the actions of the departments and agencies which discharge their responsibilities.

The Freedom of Information Law (Jersey) Law 2011 is used as a guide when determining what information is be published. While there is a presumption toward publication to support of transparency and accountability, detailed information may not be published if, for example, it would constitute a breach of data protection, or disclosure would prejudice commercial interest.

A decision made 6 July 2012

Decision Reference:   MD-PE-2012-0074 

Application Number:  EIA/2012/0721

(If applicable)

Decision Summary Title :

Jersey Gas Company Ltd, La Route du Veule, , St. Helier, Jersey,

Date of Decision Summary:

5/7/2012

Decision Summary Author:

 

Senior Planner –

K Whitehead

Decision Summary:

Public or Exempt?

(State clauses from Code of Practice booklet)

Public

Type of Report:

Oral or Written?

Written

Person Giving

Oral Report:

N/A

Written Report

Title :

Request for Reconsideration

Date of Written Report:

5/7/2012

Written Report Author:

Senior Planner –

K Whitehead

Written Report :

Public or Exempt?

(State clauses from Code of Practice booklet)

Public

Subject:  Jersey Gas Company Ltd, La Route du Veule, St. Helier, Jersey

 

Construct new LPG/Air gas production plant.

 

Decision(s):

Given the minor nature, small size and location within the existing compound, and the extent of control under other legislation, it is considered that it is unlikely that this proposal will have a significant effect on the environment, either of Jersey or elsewhere. The Minister therefore decided that an EIA is not required to support the application to construct a new LPG/Air gas production plant.

 

Reason(s) for Decision:

The nature, size or location of the proposed development, would be unlikely, if carried out, to have a significant effect on the environment, either of Jersey or elsewhere.

 

Resource Implications:

 

None

Action required:

 

Notify Agent, Applicant and all other interested parties

 

Signature:

 

Deputy R C Duhamel

PLeg / AS Initials

Position:

Minister for Planning and Environment

 

Date Signed:

 

Date of Decision (If different from Date Signed):

 

Jersey Gas Company Ltd, La Route du Veule, St. Helier (EIA/2012/0721): Environmental Impact Assessment: Not Required

Department of the Environment

Planning and Building Services

South Hill

St Helier, Jersey, JE2 4US

Tel: +44 (0)1534 445508

Fax: +44 (0)1534 445528

 

 

 

     Application Number: EIA/2012/0721

Request for Reconsideration Report of Screening Opinion

Site Address

Jersey Gas Company Ltd, La Route du Veule, St. Helier.

 

 

Requested by

Jersey Gas Co Ltd

Agent

Jersey Gas Company Ltd

 

 

Description

Construct new LPG/Air gas production plant.

 

 

Type

Environmental Impact Assessment

 

 

Zones

Waste Management Site

Built-Up Area

Regeneration Zone

Safety Zone Hazardous Install

 

 

Policies

NR8  Safety Zone for Hazardous Installation

 

Recommendation

EIA not required

 

Comments on Case

The proposal at the Jersey Gas La Collette site includes various minor equipment, new plant, pipework and storage sheds to enable Jersey Gas to operate solely from La Collette in order to de-commission the site at Tunnell Street. The works are contained within the existing Jersey Gas compound at La Collette are in comparison to the storage tanks and other works at the site, the proposal is minor in nature. However, as the proposal involves an industrial installation to carry gas, the proposal requires an Environmental Impact Assessment under Schedule 1 3(a) of the Planning and Building (Environmental Impact) (Jersey) Order 2006.

 

Under Article 2(4) of the Order, an EIA is not required if the Minister is satisfied that by virtue of factors such as the nature, size or location of the proposed development, it would be unlikely, if carried out, to have a significant effect on the environment, either of Jersey or elsewhere.

 

In order to advise the Minister if the works would be unlikely to have a significant effect on the environment, we have consulted with other States Departments. The consultations included the Health and Safety Inspectorate, Environmental Health, Environmental Protection, Natural Environment Section and Waste Regulation. All consultees are satisfied that the proposed works are of such a minor nature that an EIA is not merited in this instance. Their comments are that the requirements under other legislation for this type of work would be sufficient to ensure that the proposal does not have a significant effect on the environment.

 

Given the minor nature, small size and location within the existing compound, and the extent of control under other legislation, it is considered that it is unlikely that this proposal will have a significant effect on the environment, either of Jersey or elsewhere.

 

 

Recommendation

EIA not required

 

 

Reasons

The nature, size or location of the proposed development, would be unlikely, if carried out, to have a significant effect on the environment, either of Jersey or elsewhere.

 

 

Background Papers

1:2500 Site Plan

Consultation responses

Request for reconsideration from applicant

 

 

 

 

Endorsed by

 

Date

 


 