Skip to main content Skip to accessibility
This website is not compatible with your web browser. You should install a newer browser. If you live in Jersey and need help upgrading call the States of Jersey web team on 440099.
Government of Jerseygov.je

Information and public services for the Island of Jersey

L'înformâtion et les sèrvices publyis pouor I'Île dé Jèrri

  • Choose the service you want to log in to:

  • gov.je

    Update your notification preferences

  • one.gov.je

    Access government services

  • CAESAR

    Clear goods through customs or claim relief

  • Talentlink

    View or update your States of Jersey job application

Gunsite Flood Alleviation Scheme: Phase 2: Award of Tender

A formal published “Ministerial Decision” is required as a record of the decision of a Minister (or an Assistant Minister where they have delegated authority) as they exercise their responsibilities and powers.

Ministers are elected by the States Assembly and have legal responsibilities and powers as “corporation sole” under the States of Jersey Law 2005 by virtue of their office and in their areas of responsibility, including entering into agreements, and under any legislation conferring on them powers.

An accurate record of “Ministerial Decisions” is vital to effective governance, including:

  • demonstrating that good governance, and clear lines of accountability and authority, are in place around decisions-making – including the reasons and basis on which a decision is made, and the action required to implement a decision

  • providing a record of decisions and actions that will be available for examination by States Members, and Panels and Committees of the States Assembly; the public, organisations, and the media; and as a historical record and point of reference for the conduct of public affairs

Ministers are individually accountable to the States Assembly, including for the actions of the departments and agencies which discharge their responsibilities.

The Freedom of Information Law (Jersey) Law 2011 is used as a guide when determining what information is be published. While there is a presumption toward publication to support of transparency and accountability, detailed information may not be published if, for example, it would constitute a breach of data protection, or disclosure would prejudice commercial interest.

A decision made 8 February 2018:

Decision Reference:  MD-T-2018-0011

Decision Summary Title :

Tender Report for Gunsite Flood Alleviation Scheme Phase 2

Date of Decision Summary:

7th February 2018

Decision Summary Author:

 

Assistant Engineer

Traffic and Surveying

 

Decision Summary:

Public or Exempt?

 

Public

Type of Report:

Oral or Written?

Written

Person Giving

Oral Report:

N/A

Written Report

Title :

Tender Report for Gunsite Flood Alleviation Scheme Phase 2

Date of Written Report:

7th February 2018

Written Report Author:

Assistant Engineer

Traffic and Surveying

 

Written Report :

Public or Exempt?

 

Exempt

QE Article 33(b)

Subject: To recommend a contractor for Phase 2 of the Gunsite Flood Alleviation Scheme

Decision(s): The Minister accepted Geomarine’s Tender for the Gunsite Flood Alleviation Scheme Phase 2.

 

Reason(s) for Decision: Geomarine Ltd has provided a competitive tender and demonstrated a competent understanding of the project requirements during their involvement in Phase 1.

 

Resource Implications: Resources have been allocated from DfI Infrastructure vote.

 

Action required: Officers to notify the successful tenderer and prepare a Contract Document for signing by the Minister and Contractor.

 

Signature:

 

 

Position:

Minister for Infrastructure

 

Date Signed:

 

 

Date of Decision (If different from Date Signed):

 