Decision(s): The Minister for Planning and Environment decided to: - Approve the application to vary planning condition no. 55 (Foul Drainage) to read as follows:
“No dwelling shall be occupied until the foul drainage works to serve the development have been designed, constructed and completed to the extent necessary to permit the occupation and enjoyment of that particular dwelling unit, to the satisfaction of the Minister for Planning and Environment, in consultation with Transport and Technical Services (Drainage). Prior to the completion of the development hereby permitted, the foul pumping station shall be designed and constructed to the specification of Transport and Technical Services (Drainage) and connected to the 27 inch public gravity foul sewer adjacent to the sea wall. For avoidance of doubt, the foul water disposal shall meet the requirements set out in the comments sheet from PSD(Drainage) dated 13th October 2005 and the additional comments set out in the letter from TTS(Drainage) dated 5th December 2006 (see attached). Units 16, 50, 52-58, 60, 62, 76, 81, 90, 91, 94, 95 and 96 may be occupied in advance of the remainder of the development and of the completion of the approved foul drainage system, provided the sewage waste from these units is discharged through the permanent foul drainage system into a temporary storage tank / tight-tank formed from an adaptation of the approved foul pump station and with suitable provision for emptying the tank. Any such temporary arrangement shall be designed and implemented to the satisfaction of Transport and Technical Services (Drainage) and the Building Control department.” - Vary Planning Condition No.31 (Noise Exposure) to allow compliance with the requirements for an approved Noise Protection Scheme and the implementation of that scheme “prior to the occupation of the development hereby permitted, with the exception of plot numbers 16, 50, 52-58, 60, 62, 76, 81, 90, 91, 94, 95 and 96.”
- Vary Planning Condition No.31 (Noise Exposure) to make it clear that unit 16 as well as units 50, 52-58, 60, 62, 76, 81, 90, 91, 94, and 96 “shall be made to comply fully with the approved Noise Protection Scheme.”
- Vary Planning Condition No.14 (Security of rear access paths) to require the approval of details “prior to the occupation of the development hereby permitted, with the exception of plot numbers 16, 50, 52-58, 60, 62, 76, 81, 90, 91, 94, 95 and 96.”
- Make it clear to the developers that the decision to permit occupancy of Plot 16 is dependent on the property being signed off for occupancy by the Planning Department and the Building Control.
- Advise the developers that he will not permit any further release of plots for early occupancy in advance of the satisfactory implementation of the approved permanent foul drainage system.
|