Treasury and Resources
Ministerial Decision Report
Allocation of Discretionary Fiscal Stimulus Funding to the Department for Education, Sport and Culture in respect of a grant award to Jersey Opera House
1. Purpose of Report
The report summarises the evaluation process and resulting recommendation of the Fiscal Stimulus Steering Group (the “FSSG”) to the Minister for Treasury and Resources in respect of an allocation of funding to the Department for Education, Sport and Culture (“ESC”) for a grant award to Jersey Opera House. The grant of £112,000 is to be awarded in respect of the refurbishment of certain parts of the Opera House building to provide the organisation with improved space for performance, hospitality and office accommodation. This allocation of funding will enable the scheme to proceed to tender, after which the FSSG will evaluate the results of the tender process and evaluation and consider a recommendation to the Minister for Treasury and Resources for a further allocation of funding for the total project cost, which will then be known with certainty. The project will give a boost to the construction industry by way of releasing a project which would not take place without fiscal stimulus funding.
2. Background
As recommended by the Corporate Services Scrutiny Panel the total programme of fiscal stimulus projects includes schemes to be undertaken by both States departments and non-States organizations. This scheme will improve the Opera House building which, although occupied and operated by an organisation run independently of the States, is owned by the public of Jersey.
A bid from ESC to support a refurbishment project by the Jersey Opera House was included in the provisional programme at the beginning of 2010, although at that time it was not certain that there would be sufficient funds within the £44m fund to deliver the total project. It could only, at that time, have moved forward if a significant proportion of the total cost was available from the Opera House itself but funding constraints prevented this from happening. However, in May 2010 the FSSG considered the committed (green light) programme and remaining provisional (amber light) programme and as a result of other schemes being delivered for a lower cost than was originally anticipated, the FSSG agreed to consider funding the whole of the Opera House scheme on satisfactory confirmation of continued compliance with fiscal stimulus criteria.
3. Fiscal Stimulus Rationale
The bid was evaluated under the fiscal stimulus criteria which resulted in its inclusion in the provisional programme. As part of the FSSG evaluation underlying this recommendation those criteria were revisited and it was concluded that the project, in particular the estimated cost and planned programme, remains acceptable to proceed with an allocation of £112,000 for pre-contract costs. The allocation of funding for the full project cost, taking account of any funding which may be available from other sources at that time, will be considered following receipt and evaluation of tenders within the expected timeframe.
Furthermore, it is anticipated that progression of this project may afford other opportunities (including possible rationalisation) in relation to performance and office space currently used by other cultural organisations in Jersey, helping to achieve better value for money in a wider sense for the States and in particular ESC supported cultural activities.
4. Recommendation from the Fiscal Stimulus Steering Group
The Fiscal Stimulus Steering Group (the “FSSG”) recommends to the Minister for Treasury and Resources that a sum of £112,000 is allocated to ESC’s 2010 budget to enable onward grant payments to the Opera House for funding the pre-contract costs of the project. In accordance with procedure for schemes proposed to be fully funded with fiscal stimulus monies, the FSSG and the Minister for Treasury and Resources intend to consider the allocation of the full project cost once tenders have been received and evaluated.
5. Reason for Decision
A discretionary fiscal stimulus allocation from the Stabilisation Fund of £44m has already been approved. The project meets the key criteria for fiscal stimulus being timely, targeted and temporary and will benefit local business and individuals. The £112,000 allocation to ESC will enable grant payments to be made to Jersey Opera House to progress delivery of this stimulus project, providing work for the construction and maintenance sector.
6. Resource Implications
No financial resource implications other than those explained above.
No manpower resource implications.