Skip to main content Skip to accessibility
This website is not compatible with your web browser. You should install a newer browser. If you live in Jersey and need help upgrading call the States of Jersey web team on 440099.
Government of Jerseygov.je

Information and public services for the Island of Jersey

L'înformâtion et les sèrvices publyis pouor I'Île dé Jèrri

  • Choose the service you want to log in to:

  • gov.je

    Update your notification preferences

  • one.gov.je

    Access government services

  • CAESAR

    Clear goods through customs or claim relief

  • Talentlink

    View or update your States of Jersey job application

JEC Application to Lay New 90KV Cable - South Hill to St. Aubin's Bay Promenade

A formal published “Ministerial Decision” is required as a record of the decision of a Minister (or an Assistant Minister where they have delegated authority) as they exercise their responsibilities and powers.

Ministers are elected by the States Assembly and have legal responsibilities and powers as “corporation sole” under the States of Jersey Law 2005 by virtue of their office and in their areas of responsibility, including entering into agreements, and under any legislation conferring on them powers.

An accurate record of “Ministerial Decisions” is vital to effective governance, including:

  • demonstrating that good governance, and clear lines of accountability and authority, are in place around decisions-making – including the reasons and basis on which a decision is made, and the action required to implement a decision

  • providing a record of decisions and actions that will be available for examination by States Members, and Panels and Committees of the States Assembly; the public, organisations, and the media; and as a historical record and point of reference for the conduct of public affairs

Ministers are individually accountable to the States Assembly, including for the actions of the departments and agencies which discharge their responsibilities.

The Freedom of Information Law (Jersey) Law 2011 is used as a guide when determining what information is be published. While there is a presumption toward publication to support of transparency and accountability, detailed information may not be published if, for example, it would constitute a breach of data protection, or disclosure would prejudice commercial interest.

A decision made 17 December 2010 regarding: JEC Application to Lay New 90KV Cable - South Hill to St. Aubin's Bay Promenade

Decision Reference: MD-T-2010-0131

Decision Summary Title :

JEC 90Kv Circuit Application

Date of Decision Summary:

03 November 2010

Decision Summary Author:

 

Street Works Manager

Decision Summary:

Public or Exempt?

(State clauses from Code of Practice booklet)

Public

Type of Report:

Oral or Written?

Written

Person Giving

Oral Report:

N/A

Written Report

Title :

Jersey Electricity Company’s application to lay new 90Kv circuit from South Hill to St Aubin’s Bay Promenade (opposite Tyneville Lane) in  the highway and other public areas

Date of Written Report:

03 November 2010

Written Report Author:

Street Works Manager

Written Report :

Public or Exempt?

(State clauses from Code of Practice booklet)

Public

Subject:  Jersey Electricity Company’s application to lay new 90Kv circuit from South Hill to St Aubin’s Bay Promenade (opposite Tyneville Lane) in  the highway and other public areas

Decision(s): The Minister approved the proposed route, programme, traffic management and final road reinstatements in connection with the construction of the new 90Kv circuit in St Helier.

Reason(s) for Decision: The Minister accepted that the proposed route, programme, traffic management, road reinstatements and financial contribution of £100,000, in recognition of the cost impact of the Project to the Department, are acceptable in the light of the positive benefits of the infrastructure work to the Island as a whole.

Resource Implications: TTS street works inspections both during works and later in relation to the monitoring of reinstatements.

Action Required: Street Works Manager to inform the Jersey Electricity Company of the Minister’s decision.

Signature:

 

Position:

 

Date Signed:

 

Date of Decision (If different from Date Signed):

 

JEC Application to Lay New 90KV Cable - South Hill to St. Aubin's Bay Promenade

TRANSPORT AND TECHNICAL SERVICES

 

JERSEY ELECTRICITY COMPANY’S APPLICATION TO LAY NEW 90KV CIRCUIT FROM SOUTH HILL TO ST AUBINS BAY PROMENADE (OPPOSITE TYNEVILLE LANE) IN  THE HIGHWAY AND OTHER PUBLIC AREAS

 

 

Purpose of the Report

 

To obtain a Ministerial Decision regarding outline approval of the Jersey Electricity Company’s (JEC) proposed street works in terms of service route, programme, traffic management and final reinstatements as the ‘main road’ Highway Authority and as the Authority with responsibility for St Aubin’s Bay Promenade.

 

 

Background

 

As part of an extensive and ongoing programme of investment in their High Voltage infrastructure, the JEC is constructing a new 90Kv Switching Station at South Hill.  The Switching Station will become the central hub of the High Voltage network and will be the most strategically important element of the Island’s electricity infrastructure as it will tie together all the other major substations in the Island and once commissioned will be the termination point of the proposed third interconnector to France and any subsequent future connections that are installed.

 

As such, the project includes an extension of the 90Kv transmission network between South Hill and Victoria Avenue (opposite Tyneville Lane) in order to integrate the new Switching Station into the recently commissioned circuits between Queens Road and the Western Primary Substation located at Jersey Airport.  It is this ‘street works’ element of the project that is the subject of this report and the Ministerial Decision.

 

 

Work Details

 

In general the works will involve laying six 140 to 180mm diameter PVC ducts (to carry the 90Kv cables) over a distance of 2,365m, about 50% of which will be ‘off road’ whether in parking zones or grass verges or along the Promenade. The trench will in general be just over one metre wide (see attached typical section).  In addition three large joint bays will be constructed, one ‘off road’ near the entrance to the Tunnel and one ‘just in’ the road near the Esplanade / Castle Street junction and one opposite Tyneville Lane in the Promenade.  Cable pulling work will form the last phase of street works but will have minimal impact on traffic, etc.

 

 

Route

 

The project was first outlined by the JEC in 2007, since which time there has been an ongoing dialogue with the Department (as the project has evolved) about the optimum route. The proposed route (see attached plan) for the ducted cables has been derived from consideration of the following issues:

 

 

  • The impact of the work on the traffic network, public and road condition.
  • Compatibility with the proposed Esplanade Quarter and enabling works.
  • Available joint bay locations and road service capacity.
  • Work share opportunities (see below).

 

In addition use has been made, where possible, of the space currently occupied by an existing 33Kv transmission network (that will be decommissioned and removed) in order to provide route certainty and avoid service conflicts.

 

 

Shared Works

 

In the interest of reducing disruption to the public the Department has identified opportunities for the JEC to ‘work share’ with Cable & Wireless and Newtel Limited along the Esplanade, principally between Weighbridge Place and Castle Street.

 

Therefore, the Department has negotiated with all three companies who have agreed to this working arrangement and have appointed Geomarine Limited as their civil contractor and project co-coordinator.

 

 

Programme & Traffic Management

 

The programme (see attachment) for the street works element of the project has been principally defined by:

 

  • The commissioning date for the new South Hill Switching Station (October 2011) by which time all cabling works must be complete.
  • The programmed resurfacing of Commercial Buildings from March 2011 ahead of the commissioning of the EFW plant at La Collette later in the year.
  • Co-ordination with Cable & Wireless and Newtel network expansion works along the Esplanade, principally between Weighbridge Place and Castle Street.
  • Seasonal constraints, particularly in relation to the Esplanade between Weighbridge Place and Castle Street during December 2010 and from the end of April 2011 (i.e. Easter). Also St Aubin’s Bay Promenade from the end of April 2011.

 

The major programme / traffic impact elements of the works are summarised as follows:

 

  • South Pier / Commercial Buildings (Early October 2010 for twelve weeks): The section from South Pier up to the ‘Old Harbour’ is likely to cause disruption to commercial traffic to and from La Collette as Portable Traffic Signals will be needed. Along Commercial Buildings significant parking suspension will be required to maintain two way traffic.

 

  • Esplanade from Weighbridge Place to Castle Street (Early January 2011 for seven weeks): Eastbound traffic will be diverted along Commercial Street. This traffic management arrangement has previously worked well, with normal operation of the Bus Station possible. The critical issue is that the works will be cleared by Easter (i.e. late April) although final resurfacing (see Road Reinstatement) may not take place until the Autumn.

 

  • Esplanade from Grand Hotel to Gloucester Street (Mid February 2011 for two and a half weeks): Following a staged crossing of the Esplanade the eastbound kerbside lane of the Esplanade will be closed, potentially causing significant delays. However, this has been mitigated against, so far as it is possible, by starting the works over the Spring Half Term when traffic flows are at their lowest annual level, and carrying out evening / weekend working.

 

Otherwise works such as junction crossings, etc. will be carried out during ‘off peak’ times or out of hours such as in the evenings or on Sundays etc. as required to minimise disruption to the network.  

 

 

Negotiation Agreement

 

The Department has negotiated the following package of concessions from the JEC in relation to its’ agreement to permit the use of main roads and St Aubin’s Bay Promenade as outlined in this report.

 

Further to compliance with the ‘Specification for the Reinstatement of Openings in Main Roads’ the JEC will undertake a series  of ‘enhanced’ reinstatements as set out in the attached ‘Reinstatement Schedule’, the key ones being:

 

  • Commercial Buildings: Due to the short time period between trenching works and the road resurfacing (i.e. less than six months), Type 2 backfill material will be replaced with Foam Concrete to avoid settlement of the new road.

 

  • Esplanade: Given that the area between Weighbridge Place and Castle Street was remodelled in 2007 as part of the development of Liberation Station and is of a high level of visual importance, Type 2 backfill material will be replaced with Foam Concrete and the surface course will extend from the kerb to the road centre line. Table tops etc. will be completely rebuilt. This work will be undertaken by TTS on behalf of the JEC, Cable & Wireless and Newtel who will share costs.

 

In addition, the JEC has agreed to make a financial contribution of One Hundred Thousand Pounds (£100,000) to the Department.  The contribution is in recognition of the cost impact the project will have on the main road network and St Aubin’s Bay Promenade in terms of reduced pavement life and reduced visual acceptability, which are likely to lead to increased road maintenance and early resurfacing.

 

 

Recommendation

 

The Minister is recommended to approve the proposed service route, programme, traffic management and final road reinstatements.

 

 

Reason(s) for Decision

 

The JEC’s proposed route, programme, traffic management, road reinstatements and financial contribution (£100,000), in recognition of the cost impact of the project to the Department, are acceptable in the light of the positive benefits of the infrastructure work to the Island as a whole.


Resource Implications

 

Normal TTS street works inspections both during works and later in relation to the monitoring of reinstatements.

 

 

Action Required

 

Street Works Manager to inform the JEC of the Minister’s decision.

 

 

 

Written by:

Street Works Manager

 

Approved by: 

Director, Municipal Services

 

Attachments:

Summary Route Plan & Typical Cross Section, Summary Project Programme, Reinstatement Schedule.

 

 

 

  

 

WR JEC Application to Lay New 90KV Cable.docI:\Minister\2010\Ministerial Decisions\MD 00 JEC Application to Lay New 90KV Cable\WR JEC Application to Lay New 90KV Cable.doc

Back to top
rating button