08 May 2025
Work to fill the voids caused by the burst water main has now been completed.
Concrete to underpin parts of the building was poured on Wednesday and
Structural Engineers have now given approval for the road to open once the
concrete has gained sufficient strength over the weekend.
Inspection and monitoring will continue next week to ensure all measures taken
have been effective.
Road markings have been repainted in preparation for reopening.
Pedestrian access through Rouge Bouillon will remain in place throughout the
bank holiday weekend.
The project remains on schedule, with the road due to reopen before the
morning rush hour on Monday 12 May, once all safety measures are confirmed.
This will be the final scheduled update.
For more information and the latest schedule of works, please visit: Gov.je.