About the project
Infrastructure and Environment (IE) will extend the existing gravity sewage network in the Les Charrieres de Bonne Nuit and La Rue de la Porte catchment.
The works should take place from Monday 15 July to Monday 23 December 2024.
For more information call the Liquid Waste Project Team on +44 (0) 1534 445509 or email
LWCapitalDelivery@gov.je.
Schedule of work
Find the schedule and working hours below.
Monday 15 July to Monday 23 December 2024 | Monday to Friday, 8am to 6pm Saturday, 8am to 1pm | Road closure of Les Charrieres de Bonne Nuit and La Rue de la Porte from the junction with Les Nouvelles Charrieres de Bonne Nuit up to the junction of La Rue de la Porte and La Route du Mont Mado.
|
---|
Diversion route
Diversion route map for Bonne Nuit
Into Bonne Nuit bay:
La Route du Mont Mado, La Rue de la Mare des Pres and Les Nouvelles Charrieres.
Out of Bonne Nuit bay:
Les Nouvelles Charrieres, La Rue de la Mare des Pres and La Route du Mont Mado.
Access
Access to all businesses and premises will be maintained during the works.
Buses
The following bus stops will be suspended until Wednesday 11 December:
- La Porte 2879
- Falaise de Fremont 4283
- Bonne Nuit Bay E 2434
- La Mare des Pres S 4296, suspended in the inbound direction (going to Liberation Station)
Find more information on
LibertyBus.