Bellozanne Electricical Sub-Station: Construction of New Building: Tender Award

A formal published “Ministerial Decision” is required as a record of the decision of a Minister (or an Assistant Minister where they have delegated authority) as they exercise their responsibilities and powers.

Ministers are elected by the States Assembly and have legal responsibilities and powers as “corporation sole” under the States of Jersey Law 2005 by virtue of their office and in their areas of responsibility, including entering into agreements, and under any legislation conferring on them powers.

An accurate record of “Ministerial Decisions” is vital to effective governance, including:

  • demonstrating that good governance, and clear lines of accountability and authority, are in place around decisions-making – including the reasons and basis on which a decision is made, and the action required to implement a decision

  • providing a record of decisions and actions that will be available for examination by States Members, and Panels and Committees of the States Assembly; the public, organisations, and the media; and as a historical record and point of reference for the conduct of public affairs

Ministers are individually accountable to the States Assembly, including for the actions of the departments and agencies which discharge their responsibilities.

The Freedom of Information Law (Jersey) Law 2011 is used as a guide when determining what information is be published. While there is a presumption toward publication to support of transparency and accountability, detailed information may not be published if, for example, it would constitute a breach of data protection, or disclosure would prejudice commercial interest.

A decision made 14 December 2012:

Decision Reference:  MD-T-2012-0098

Decision Summary Title :

Tender Report for New Electrical Sub-Station Building at Bellozanne

Date of Decision Summary:

06 December 2012

Decision Summary Author:

 

Head Electrical Engineering Manager

Decision Summary:

Public or Exempt?

(State clauses from Code of Practice booklet)

Public

Type of Report:

Oral or Written?

Written

Person Giving

Oral Report:

N/A

Written Report

Title :

Tender Report for New Electrical Sub-Station Building at Bellozanne

 

Date of Written Report:

06 December 2012

Written Report Author:

Head Electrical Engineering Manager

 

Written Report :

Public or Exempt?

(State clauses from Code of Practice booklet)

Exempt

3.2.1(a)(xii)

Subject:  Tender report for the construction of a new Electrical Sub-Station Building at Bellozanne.

Decision(s):  The Minister accepted the appointment of Houze Construction Limited as the favoured contractor at the tender price of £184,750.00.

 

Reason(s) for Decision: Accepting this tender would provide best value for the department and for the works to be undertaken in a timely manner.

 

Resource Implications:  Approximately 17% of the capital allocation associated against a £1.05m TTS Capital Fund apportioned to this section of infra-structure replacement/upgrade work.

 

Action required:  Officers to advise Houze Construction Ltd of the acceptance of their tender and arrange work to be undertaken.

 