Skip to main content Skip to accessibility
This website is not compatible with your web browser. You should install a newer browser. If you live in Jersey and need help upgrading call the States of Jersey web team on 440099.
Government of Jerseygov.je

Information and public services for the Island of Jersey

L'înformâtion et les sèrvices publyis pouor I'Île dé Jèrri

  • Choose the service you want to log in to:

  • gov.je

    Update your notification preferences

  • one.gov.je

    Access government services

  • CAESAR

    Clear goods through customs or claim relief

  • Talentlink

    View or update your States of Jersey job application

Electronic Patient Records system (FOI)

Electronic Patient Records system (FOI)

Produced by the Freedom of Information office
Authored by Government of Jersey and published on 08 February 2024.
Prepared internally, no external costs.

​​​Request

A

Please advise what the current state of progress with the new 'Electronic Patient Records' system (EPR) is?

B

What is the target delivery date and Is this being met?

C

Does the system comply with the specification or brief?

D

Is the project on budget?

E

Has the project encountered any problems?

Response

A

In May 2023, Health and Community Services’ TrakCare Electronic Patient Record (EPR) system was replaced with the IMS MAXIMS solution. The complete functionality of the new EPR will be rolled out over four years in five releases. Releases 1 and 2 were completed in June 2023. Release 3 is due for completion in Quarter 3 of 2024, Release 4 in Quarter 4 of 2024, and Release 5 in Quarter 1 of 2025.

B

The new EPR system implementation is on schedule to meet its target completion date of Quarter 1, 2025.

C

The system aligns with agreed specifications, with the exception of the maternity module. The third-party supplier originally selected for the maternity module is unable to meet the required specifications within the agreed timeline. Engagement with a replacement supplier is currently underway.

D

The project operated within budget in 2023 and is currently projected to stay within budget for 2024.

E

Implementing a new EPR system comes with both technical and business change complexities which, as expected, present challenges. However, the project is successfully achieving its expected outcomes, with no significant incidents or major issues reported.