Skip to main content Skip to accessibility
This website is not compatible with your web browser. You should install a newer browser. If you live in Jersey and need help upgrading call the States of Jersey web team on 440099.
Government of Jerseygov.je

Information and public services for the Island of Jersey

L'înformâtion et les sèrvices publyis pouor I'Île dé Jèrri

  • Choose the service you want to log in to:

  • gov.je

    Update your notification preferences

  • one.gov.je

    Access government services

  • CAESAR

    Clear goods through customs or claim relief

  • Talentlink

    View or update your States of Jersey job application

Work on Snow Hill rock face

16 September 2015

Work to stabilise the rock face above Snow Hill car park will begin on Monday 21 September.

The essential works to the area above the ‘concrete catcher’ is the final part a wider project commissioned by Jersey Property Holdings to support the Fort Regent rock faces. The high risk areas for work had been highlighted in a detailed structural survey carried out in 2011.

During different phases of the work, areas of the Snow Hill car park will be closed to ensure public safety but pedestrian footpath access and access to the motorbike and bicycle parking areas at Hill Street /Snow Hill will be maintained throughout the work.

Work suspended over Christmas

With the agreement of the Transport and Technical Services Department (TTS) the work will be suspended over the Christmas period so that short stay shopper parking will not be disrupted. Unavailable spaces will be cordoned off.

Jersey Property Holdings have awarded the contract for the work to local company Geomarine Ltd.

Transport and Technical Services Minister and Assistant Treasury Minister with responsibility for Jersey Property Holdings, Deputy Eddie Noel, said “The final stage of this project will ensure the long term stability of the rock face around Fort Regent and ensure the safety of the public using Snow Hill car park. We are pleased to be able to award the contract for this work to a local company through a competitive tendering process.”

Phase One

​Location​Area nearest the motorbike parking
​Number of parking spaces unavailable ​20
​Start date​Monday 21 September 2015
​End date​Thursday 5 November 2015
​Duration​Seven weeks


  

Phase Two

​Location​Middle section of rockface
​Number of spaces unavailable​28
​Start date​Friday 6 November 2015
​Work suspended for Christmas shoppers​Monday 30 November 2015 to
Monday 4 January 2016
​End date ​Friday 22 January 2016
​Duration​Six weeks


 

Phase Three

​Location​Entrance of car park section of rock face
​Number of parking spaces unavailable 33
​Start date​Monday 25 January 2016
​End date​Friday 4 March 2016
​Duration​Six weeks