About the project
As part of the ongoing highway maintenance by Infrastructure, Housing and Environment, the Esplanade's carriageway is being reconstructed between the junction with Gloucester Street and the junction with Peirson Road.
This project is split into 4 sections. Each section will be constructed during the school holidays.
Schedule of work
Section 1 (completed)
| Completed October half term 2021
| Lane 1 and half of lane 2 westbound carriageway
|
---|
Section 2
| Provisionally October half term 2024
| Lane 3, half of lane 2 and right turn lanes westbound carriageway
|
---|
Section 3
| Provisionally October half term 2023
| Lane 3 and half of lane 2 eastbound carriageway
|
---|
Section 4 (completed)
| Completed October half term 2022
| Lane 1 and half of lane 2 eastbound carriageway
|
---|